Издание на английском языке
The book is a guide to the management of ballast water and sediments on ships in accordance with the requirements of the International Convention on the Control and Management of Ballast Water and Sediments. It describes the objectives and procedures necessary to comply with international standards, including IMO recommendations. The focus is on standard operating practices that help ship owners and captains effectively monitor and manage ballast water, ensuring safety and environmental protection. The book also highlights the importance of regularly updating information and the need for a translation into the crew's working language if the text is not written in English, French or Spanish.
Contents
Ballast Water Management Plan
1. Ship particulars
2. Introduction
3. Record of circulation
4. Record of Amendments
5. Purpose of the Plan
6. Plans and drawings of the ballast system
7. Description of the ballast system
7.1 Ballast tank data
7.2 Dual Use Ballast tank data [delete if not applicable - amend as appropriate]
7.3 Pump(s) data
7.4 Ballast Water Treatment System Data [delete if not applicable]
7.5 Overflow and filling line data (for flow through and dilution method) [delete if not Applicable]
8. Ballast water sampling points
8.1 Sampling for compliance with the ballast water exchange standard
8.2 Sampling for compliance with the ballast water performance standard [delete if not applicable]
9. Operation of the ballast water management system
9.1 Ballast water exchange
9.1.1 Sequential method [delete if not applicable]
9.1.2 Flow through method [delete if not applicable]
9.1.3 Dilution method [delete if not applicable]
9.2 Ballast Water Treatment Systems [delete if not applicable]
9.3 Precautionary practices
9.3.1 Minimising uptake of harmful aquatic organisms, pathogens and sediments
9.3.2 Non-release or minimal release of ballast water
9.3.3 Discharge to reception facilities
9.4 Temporary storage of treated sewage (TS) and / or Grey Water (GW) in Ballast Tanks
9.4.1 General
9.4.2 Change-over procedure from ballast water storage to TS/GW storage
9.4.3 Change-over procedure from TS/GW storage back to ballast water storage
9.4.4 Discharge of Ballast Water and TS/GW from Ballast Tank(s) designated for holding TS/GW
10. Safety procedures for the ship and the crew
10.1 Exchange at sea
10.1.1 Safety considerations
Sequential method [delete if not applicable]
Flow through method [delete if not applicable]
Dilution method [delete if not applicable]
10.1.2 Conditions under which ballast water exchange at sea should not be undertaken
10.1.3 Precautionary advice to Masters when undertaking ballast water exchange operations
10.2 Ballast Water Treatment [delete if not applicable]
11. Operational or safety restrictions
11.1 Ballast water exchange
11.2 Ballast water treatment [delete if not applicable]
11.3 Procedures for safe tank entry
12. Description of the methods used on board for ballast water management and sediment control
12.1 Procedures for ballast water exchange
12.2 Procedures for ballast water treatment [delete if not applicable]
12.2.1 Ballast Water Treatment System particulars
12.2.2 Operation of the Ballast Water Treatment System
12.2.3 System design limitations
12.2.4 By-pass of the Ballast Water Treatment System
12.2.5 Multi-purpose tanks [delete if not applicable]
12.2.6 Handling of untreated ballast water
12.2.7 Health and Safety
12.2.8 Control and Monitoring Equipment
13. Procedures for the disposal of sediments
14. Methods of communication
14.1 Action to be taken by the vessel when the coastal state has specific procedures for discharge of ballast water
14.2 Action to be taken by the vessel when the coastal state has no specific procedures for discharge of ballast water
15. Duties of the Ballast Water Management Officer
16. Recording requirements
16.1 Ballast Water Record Book
16.2 Sediment removal and tank flushing log
17. Crew training and familiarisation
17.1 Training record for ballast water management manual
18. Exemptions
Appendices
Appendix 1 - Plans
Appendix 2 - Assessment criteria for the sequential method [delete if not applicable]
Appendix 3 - Ballast exchange sequences
Appendix 4 - National or local requirements
Appendix 5 - Reference documents
Appendix 6 - Ballast Water Record Book
Appendix 7 - Guidance for compliance with BWM Convention for ships operating in Challenging Water Quality (CWQ) conditions